ABOUT US
CONTACT US
line-header

+64 (09) 299 9767

info@heronconstruction.co.nz

Port Capacity Project - Maritime Works Package

Project: Port Capacity Project - Maritime Works Package (Webb Dock)
Location: Port of Melbourne, Victoria
Client: Port of Melbourne

 
Machiavelli Webb Dock 1-888   

The Port of Melbourne is Australia’s largest and busiest container port, and also one of Australia’s largest general cargo ports. Forty-two container lines, and several general and bulk cargo carriers make more than 3,200 ship calls a year to Melbourne, and the Port operates 24 hours/day, 365 days per year.

The Maritime Works Package was awarded to McConnell Dowell and Heron Construction in March 2014, and that October Heron mobilised the Machiavelli and two split hopper barges to Webb Dock and commenced dredging 1.1 million m3 of material to a design depth of 13.5 and 15.5m. Dredging of the first area was completed on schedule and the first 500m of wharf was handed over to the Port of Melbourne Corporation on time.

This complex project required the use of lockout systems on the dredge to prevent contacting with underwater structures including a submerged combi-pile structure. In a world first, a dredge spud system was also used to improve the material model for the project, and all wharf faces were water jetted using an underwater pump attached to the bucket of the Machiavelli.

During the project, Heron took delivery of two new 1,200m3 split hopper barges, and the innovative addition of stern thrusters significantly improved the turnaround for barge changes.

All material placed in the Port’s dredge material ground (DMG) required tracking and pinpoint accuracy of placement. In total, more than 2,700 barges of material were placed on underwater bund walls or in the DMG. Four kilometers of bund wall was trimmed by the Machiavelli, vastly improving the storage capacity of the DMG for the Port of Melbourne Corporation.

Three additional stages of the project were handed over as scheduled or ahead of time, with a total dredge volume of more than 1.8 million m3.

At handover all dredge areas and disposal areas met the stringent design criteria of the Port Capacity Project, and the project was completed with 150,000 man hours LTI free.

Winner: Australian Construction Achievement Award 2017
 

  ACAA-2017-Winner-photo-639

ABOUT US

Heron Construction is a family owned and operated marine construction company that specialises in using backhoe dredgers for marine dredging. Established in 1964, our team has been providing construction companies with a quality dredging service for over 45 years.

FIND OUT MORE ABOUT OUR TEAM   arrow link
 
PROJECTS
As Heron celebrates 50 years of operation, it can look back on a wide range of successful projects.
 
CONTACT US
 
icon phone +64 (09) 299 9767
icon mail info@heronconstruction.co.nz

icon location
 
Heron Construction Co Ltd.
PO Box 72561
Papakura 2244
New Zealand